Rotary Car Dumper

  • Location: Norfolk, Virginia
  • Owner: Norfolk Southern
  • Fenton Project Manager: Garry Miller
  • Fenton Project Superintendent: John Wurlzabacher

Many of Fenton's customers are the leaders in their industry and our job is to make sure their operations are running at top speed and they stay at the top of their game. Fenton was contracted by Norfolk Southern to complete a major upgrade to its Lamberts Point export coal facility in Norfolk, Virginia. The project was crucial in maintaining their facility as the largest and fastest coal transload facility in the Northern Hemisphere.

Fenton’s scope of work was to completely overhaul their coal dumper system over two separate 90-day periods. The dumper system consists of two pairs of dumpers, each pair handling two coal cars at a time, which rotate the cars 135 degrees and dump their contents into a conveyor system that transports the coal to the pier. The upgrade consisted of replacing the structural steel that supports the dumpers and the hopper bins that funnel the coal onto the conveyor belts. The dumpers, at 500,000 pounds each, were lifted by cranes and placed on the ground, so as the steel upgrades could take place. Concurrently with the dumper overhaul, both loaders received complete electrical overhauls, including replacement of the main generator sets with solid-state drives and new power transformers and control and monitoring systems.

Rotary Dumper (1) Rotary Dumper (2) Rotary Dumper (3) Rotary Dumper (4) Rotary Dumper (5) Rotary Dumper (6) Rotary Dumper (7) Rotary Dumper (14)

Right Photo

Contact Us







Testimonials

"We appreciate the commitment to excellence and safety you have shown while in our service." - OP Collins and GA Davis, Norfolk Southern Corporation